Barge operators that use the Illinois Waterway will face the first round of closures in June as preliminary work begins on major repairs to six of eight lock and dam sites along the system that will begin next summer and carry into 2023.
In preparation for significant work next year, bulkhead slots will be installed at Marseilles and Starved Rock locks this summer, requiring a partial closure and width restrictions for 92 days. A full lock closure will then occur for 14 days to install the sill...