The St. Simons Sound Incident Unified Command working on the salvage of the capsized car carrier Golden Ray says that cutting and lifting operations on the wreck will be delayed for several weeks.
The delay has been caused by the need for engineers to modify the mooring system for the the twin-gantry, twin-barge heavy lift catamaran VB-10,000 at the wreck-site.
Engineers with the response designed an array of five anchors that accounted for multiple challenging variables such as extreme currents...