CBO Says Navy Underestimated Cost of First Frigate by 40 Percent

Italian FREMM, the basis for the FFG-62 program. Fincantieri Marine Group Image

The lead ship in the Navy’s next-generation frigate class could cost $1.6 billion, a figure that is 40 percent above the service’s projections for the first-in-class vessel, according to the Congressional Budget Office.

A new report from CBO approximates the cost for the first 10 ships in the FFG-62 program, formerly FFG(X), at $12.3 billion.

“Using three other surface combatants—the Arleigh Burke Flight III, the...

https://news.usni.org/2020/10/14/cbo-says-navy-underestimated-cost-of-first-frigate-by-40-percent